Supply and installation of earthing and bonding for two rail signal buildings including:
- embedded welding of building slabs
- 4 x 4m and 6 x 20m electrodes
- stainless steel buried grading ring
- connections into the buildings
The projects required Earthing Solutions’ specialised drilling equipment as well as specialised materials and installation methods such as exothermic welding.
The Challenge:
The projects were challenging with the location being in the live rail corridor.
Result:
The Earthing Solutions’ crews together with the British Concrete project management team completed the projects on time and budget.