Supply and installation of earth grid including:
- 120mm2 bare earth grid
- cadweld connections
- ductor testing of inground connections
- 3m electrode
- embedded welding of equipment slabs including bonding connections and testing.
Challenge:
The project was carried out under tight access conditions and within a narrow installation timeframe. Flexibility and close coordination with other contractors was required. Safety was a high priority throughout, and the project was completed on time and without incident.
Result:
The project was completed successfully to the design requirements and to the client’s satisfaction.