Project Details

Client: Lanskey Constructions on behalf of Endeavour Energy

Type: Zone Substation Earth Grid Installation

Date: 2013 to 2015

Scope of project:

Supply and installation of complete earth grid installation including buried earth grid, surface mounted earth grid, crimped connections, connections to fence post and gates.

The project also included supply and installation of 10 x 15m-deep earth electrodes.

Supply and installation of complete earth bar and connections was carried out in basement of substation, this work requires skilled personnel and specialised equipment and was completed successfully.

The project required the supply and installation of 3 x 20m lightning masts inclusive of steel reinforced foundations and coordination with the client for access restrictions. The lightning masts were installed with a city crane.

The project required tight safety measures as the temporary substation was present at all times of construction.

The project also required tight coordination with the Earthing Solutions and Lanskey Constructions management teams. The project was managed by Endeavour Energy for compliance with standards and the projects were completed on budget and on time in 2015.