Earthing and Lightning Protection | Call Earthing Solutions (02) 9608 9844    LinkedIn logo

Substation Earthing

box hill zone substation earthgrid installation

Box Hill Zone Substation

Earthing Solutions supplied and installed a complete earth grid for the Box Hill Zone Substation. The project involved: 1800m buried earth grid Surface-mounted earth grid Crimped connections, connections to fenceposts and gates Supply and installation of deep earth electrodes Supply and installation of complete embedded earthing in the transformer bay Continuity testing Supply and installation […]

Box Hill Zone Substation Read More »

Roberts Road Zone Substation

Roberts Road Zone Substation

Complete installation of a buried earth grid including: Approximately 2000m earth grid Bonds to equipment 15m electrode and connections Embedded welding Testing for structure footings. Challenge: Earthing Solutions had to work in and around existing live structures and coordinating with Endeavour Energy and the various trades involved in the project was challenging. Given the 6-month

Roberts Road Zone Substation Read More »

kiosk transformer leura

Kiosk Transformer Leura

Supply and installation of multiple high voltage and low voltage electrodes and earth grid. The project involved drilling to install the electrodes, preparing the electrode inspection pits, excavating and back filling trenches, exothermic welding for electrode connection, and 3 pole FOB testing. Challenge: With the project being within the rail corridor, Earthing Solutions had to

Kiosk Transformer Leura Read More »

Minto Traction Substation earthing and bondi

Minto Traction Substation

Supply and installation of earthing and bonding for Sydney Trains Traction Substation including: 8 x electrodes 70mm2 buried grading ring 3x transformer bunds in the basement ground floor equipotential earth bar fitout bonds to equipment and structure. Installing the earthing and bonding system required specialised drilling equipment and specialised materials. Challenege: The project required careful

Minto Traction Substation Read More »

pactum glass ingleburn private substation earth grid project

Pactum Glass Ingleburn

Supply and installation of combined earth grid for private substation including: 70mm2 bare c/u grading ring 70mm2 G/Y insulated cable to main earth bar 4 x 10m-deep earth electrodes Cadweld connections Furse electrode pits and testing. The supply and installation of the earth grid components of the project required experienced staff and specialised excavation and

Pactum Glass Ingleburn Read More »

Oran Park Zone substation earth grid project

Oran Park Zone Substation

Supply and installation of complete earth grid system including buried earth grid, surface mounted earth grid, crimped connections, and connections to fence post and gates. The earth bar and connections were installed in the substation basement. The work required skilled personnel and specialised equipment. The project also included the supply and installation of 10 x

Oran Park Zone Substation Read More »

Potts Hill lightning protection and substation earthing

Potts Hill Transgrid Substation

Supply and installation of complete earth grid and lightning protection installation including: 40 x 6m deep earth electrodes Buried earth grids Surface mounted earth grids Crimped connections Connections to fence posts and gates Lightning protection Surface, wall and ceiling mounted earth grid Connections to 132 and 330 GIS equipment The installation of earthing components in

Potts Hill Transgrid Substation Read More »